This was our filming schedule, made by Gio/Carrick.
No. | Scene | Date | Location | People | Props | Equipment | Other |
1 | 1 Church (at convention) | 31st August 2024 (Subject to Change) | Hillsong Bali Campus | Giorgio - Director and Cameraman | Fake Pistol | Camera Microphone Light | Time to get to location is 1 hour + |
Carrick - Actor and Ast. Director |
Kaka - Actor | Suit and Tie | Traffic is a big issue |
Jaden - Ast. Cameraman |
2 | 2 Interview 1 | 25th August 2024 | Ps. Brian's House | Carrick - Director and Cameraman | | Have to adjust around Pastor's work schedules and church schedule |
Ps. Brian - Actor |
3 | 3 Interview 2 | 25th August 2024 | Potter's House Bali | Carrick - Director and Cameraman | | Have to work around private arrangements and church schedule |
Jeremiah Tui - Actor |
4 | 4 Interview 3 | 25th August 2024 | Carrick's House | Carrick - Director and Cameraman | Police Uniform | |
Ed - Actor |
5 | B Roll 1 | 24th August 2024 | Lapangan Renon | Giorgio - Director and Cameraman | | Camera | |
6 | B Roll 2 | 26th August 2024 | Regents School | Giorgio - Director and Cameraman | Australian Flag | |
Self-Reflection: I'm honestly surprised that, for the most part, we were consistent with the schedule, or at least got what we need done on time XD
These 8-9 weeks of working on the project have felt short. Imagine next term with just 7 weeks...